A filtration project can have approved designs, substantial concrete work and a future operating deadline at the same time. For Portland, Oregon, read what each update says has happened.
The Water Bureau’s 9 October 2026 newsletter says the Bull Run supply is still unfiltered. It describes the new facility as under construction. That dated statement keeps descriptions of future filtration benefits from being mistaken for treatment already in service.
Read the reporting period before the percentage
The monthly status page, explicitly updated on 1 October 2026, reports the project as 41.00 percent complete at the end of August 2026. The page update and the progress measurement refer to different dates.
When opening the page in October, retain its August reporting boundary. The figure is not a fresh measurement for the day of the visit. Nor does a percentage say which individual treatment processes have been tested, commissioned or connected to customers.
Keep the milestone’s wording with the figure. A pipe installed, a structure built and filtered water being delivered describe different evidence. A progress photo can help explain construction, but it cannot supply an operating date that the accompanying notice does not state.
Keep the deadline version with the date
The Bureau’s 19 February 2026 press release described a request for a 24-month extension to the September 2027 deadline. At that point, the notice reported a request to the Oregon Health Authority.
The project overview currently lists 30 September 2029 for delivering filtered water. It attributes that deadline to the City’s bilateral compliance agreement with the Authority. The linked signed amendment could not be retrieved for this article; the deadline here is the City’s reported position.
Older references to 2027 remain useful for understanding the project’s history. They should not be silently substituted for the newer overview. A future deadline does not mean filtration has started.

A completed basin is a construction milestone
The overview distinguishes completed planning work from construction. It lists pilot-study and preliminary-planning submissions in 2020 and final construction plans and schedule in 2022. Those are completed document milestones, not operating-treatment milestones.
The October newsletter gives a more recent example. Crews completed the final slab-on-grade pours for the filters in September. The same account describes pipe-gallery, decking and mechanical process-piping work as later steps. A sentence about completed slabs therefore does not mean every part of the filter area is finished.
When tracking a project, look for the noun after “completed.” Is the utility discussing a submission, an excavation, a concrete pour, commissioning or delivery of water? Preserve that distinction when sharing an update with someone else.

Check again when the source changes
For a trip or a question about present treatment, reopen the utility’s current overview and dated news. Read the stated operating position separately from the construction programme.
These sources were accessed on 15 October 2026 in Europe/Berlin, while it was 14 October in Portland. That is our editorial check date, not a utility publication or a new Pacific-local operating snapshot. Our Portland city guide supplies broader travel guidance; the milestones above explain how to follow the filtration project without promoting a plan into a finished works.